Scaffolding Moved to Allow Additional WindowStabilization Work to Proceed As of the week of August 21st, the scaffolding surrounding the outer perimeter of the mill has been disassembled and a portion of it moved to interior. This allows the stone masons to gain access to inside window areas on the south wall. All four interior walls now have scaffolding erected alongside them.
Exterior View of the Mill on August 22ndThe stone mansonry and window timbering efforts continue to proceed in a satisfactory manner. Additional materials have been arriving on-site to support this portion of the stabilization endeavor.
Window Timbers Awaiting InstallationSome vegetation in the line-of-sight of Interstate 66 has been cleared by volunteers in order to provide a less obstructed view of the front of the building and the Chapman's Mill web site sign.
![]() View of Installed Timber as Seen Through Window Opening from the East Side of the Building Dennis Van Derlaske
|