| Last update Oct 3, 2007 |
Stabilization UpdatesWeekly progress on Chapman's Mill |
| 05-04-06 | Stabilization gets underway | |
| 05-11-06 | Initial work scaffolding erection | |
| 05-23-05 | Corner drilling nears completion | |
| 05-31-06 | Insertion of Corner Anchors to Start | |
| 06-06-06 | Corner Anchor Complete Window Anchoring Started | |
| 06-13-06 | Window Anchoring Continues Window Anchoring Continues | |
| 06-20-06 | Window Anchoring Nears Completion | |
| 06-27-06 | Stabilization Work Progresses Despite Inclement Weather | |
| 07-11-06 | Progress Midway on Long Vertical Anchors | |
| 07-25-06 | Anchoring Complete | |
| 08-15-06 | Window Area Masonry Work Commenced | |
| 08-23-06 | Window Masonry Work Commenced | |
| 05-16-07 | Next Phase begins | |
| 05-25-07 | Beam Reinforcement status | |
| 05-31-07 | Stone Masons Commence Mortar Injection | |
| 07-14-07 | Stabilization of Mill Store Structure Underway | |
| 07-18-07 | Reinforcing Steel Arrives on Site Installation Begins | |
| 07-20-07 | Masons Complete Stabilization Work on Store | |
| 08-20-07 | Installation of Window Lintels | |
| 09-13-07 | Steel Bracing Installed | |
| 09-30-07 | Final Stone Window Lintel | |
| 04-22-07 | Press Release |